Silicon Valley BART finishes the 83-foot shaft where its tunnel boring machine will start
The SJtoday team
If you've wondered whether Silicon Valley BART is really happening, you can now point to a hole in the ground. Workers finished excavating and reinforcing an 83-foot-deep launch shaft on a former rail yard near PayPal Park. It's where the machine that digs the 5-mile tunnel will begin.
- Tunneling: expected to begin in early 2028
- Boring machine: 53 feet wide, digs 30 to 40 feet a day
- Tunnel dig: projected to take 40 months
- New stations: three in San Jose, one in Santa Clara
The $12.7 billion project, overseen by VTA, started as a $4.7 billion plan with a 2026 opening unveiled in 2014. A pandemic spike in material costs and other factors more than doubled the price and pushed the expected opening to 2037.
Silicon Valley BART's price tag grew from $4.7 billion to $12.7 billion
Sources: Local News Matters, SFGATE
View as table
| Value | |
|---|---|
| 2014 plan | $4.7 billion |
| Current cost | $12.7 billion |
“You can really feel where the trains will go and imagine that someday a subway is going to run here.”
The BART extension's shaft is done, with tunneling still ahead
- 2014Officials project a $4.7 billion extension opening in 2026.
- Sept. 2026Workers complete excavation at the launch shaft site.
- Oct. 2026Crews finish pouring concrete for the underground structure.
- Early 2028Tunneling is expected to begin.
- 2037Expected opening date, pushed back from 2026.