City HallMonday, November 16
San Jose leaders propose pausing data center approvals until new rules get a vote Dec. 8
The SJtoday team
If you've followed the data center fight, here's the latest. Mayor Matt Mahan and Councilmembers Pamela Campos, David Cohen, Peter Ortiz and Domingo Candelas proposed Thursday pausing land use approvals for data centers until the City Council votes on standards Dec. 8. That comes after reports that Google's Alviso project at 5087 Disk Drive could be approved first.
Google's Alviso project would need a lot of power
- 250 megawatts
- the Disk Drive project would require
- 250,000
- households that much power could supply
- 16
- data center projects in San Jose's development pipeline
Source: Local News Matters
- Proposed power rule: 100% clean energy
- Proposed cooling rule: no open-loop systems
- Proposed generator rule: run only during outages
- Proposed bans: NDAs and public subsidies
Advocates say the pause falls short. Linda Hutchins-Knowles of Mothers Out Front Silicon Valley said:
“I definitely appreciate there being a pause put now to stop any more getting through, but I still think that needs to be extended beyond their current timeline”
Want to weigh in? The District 4 data center town hall is tonight, 6:30 to 8:30 p.m. at The South Bay Yacht Club, and it's free. The Planning Commission takes up the latest standards Wed., Nov. 18.
The data center standards head toward a council vote
- Nov. 12Mahan and four councilmembers announce a proposed pause on data center approvals.
- Nov. 16District 4 data center town hall runs 6:30 to 8:30 p.m.
- Nov. 18Planning Commission considers the latest version of the standards.
- Dec. 8City Council is scheduled to vote on the data center standards.
Sources: Local News Matters, CBS San Francisco, Eventbrite